 Pipeline Rehabilitation Signs the big Contract again 
-CHD Zouxian Power Plant project 
CHD Zouxian Power Plant  
  
   Our company recently signed “the three periods water supply pipeline lining and modification project contract of Zouxian Power Plant with CHD Zouxian Power Plant,  
the contract total cost is RMB 137 million Yuan, we signed the contract successfully to renew pipeline repair business records again. At the same time, according to the  
Chinese geological society of trenchless technology professional committee to understand that the above contract is by far the biggest contracts in the domestic  
trenchless repair old pipeline technology industry, the longest pipeline rehabilitation and reconstruction project, the implementation of this contract will have the positive 
impact in the future to the company's main business trenchless repair old pipeline technology results improving, at the same time greatly enhance the core  
competitiveness of the company. 
  Company design uses trenchless repair old pipeline construction technologyHDPE lining method, the project length of 80 km, diameter of DN900 DN1000, plan to complete in six years. HDPE lining method in 2001 gained the appraisal certificate of science and technology achievement of the ministry of construction,  
this technology has been passed for 15 years maturely. In 2007 we took the old pipeline repair concept to the owner, our company with first-class service, first class technology successfully won the bid in the number of bidders. 
Aerial view of CHD Zouxian Power Plant 
  
Plant corner of CHD Zouxian Power Plant  
  CHD Zouxian Power Plant has been my company's old customer, it is a modern oversize pithead power plant, as a wholly owned enterprise of Huadian power  
international Co.,Ltd, currently installed 4 sets 335000 kw, 2 sets 600000kwand 2sets 1000000 kw units, the total capacity of 4.54 million kw, which is the  
project of imported technology localization of domestic first million kilowatts of supercritical thermal power unit, and listed as national key construction project. The signing of this contract is the affirmation of the technology and service trust of my company, so we must deliver and create brilliant again. 
                 |