Congratulations to Yunnan Xuanwei pipeline installation project’ successful completion in the installation branch
Yunfeng branch φ720 start the installation of water supply pipes have ocean reservoirs, pumping stations west end point, length of 4616 meters. Along the hillside, laying paddy fields; the terrain is more complex site access difficult. Line a total of 46 elbows, 2 valves, a flow control, six rivers (canals) across, one through. Pipe installation project at the head offices of all functional departments and Yunfeng strong support, the project manager Xue Jinghua comrades set a good example and lead the people to overcome the pipe out of luck comes into play is difficult, the weather was rainy and other difficulties; from the procurement of steel, corrosion to the installation, PaulQuality, quantity, safety, completed 15 days ahead of the construction task, by the construction unit of praise.
|